Three men A, B and C working together can do a work…
Three men A, B and C working together can do a work in 17 days. They start the work together and A works for 5 days and takes rest on the sixth day, B works for 5 days and takes rest on the next two days and C works for 8 days and takes rest on the next three days. In how many days will the work be completed ? (A, B, C work at the same rate)