If 'A' completes a piece of work in 3 days, which 'B'…
If 'A' completes a piece of work in 3 days, which 'B' completes it in 5 days and 'C' takes 10 days to complete the same work. How long will they take to complete the work , if they work together?
AQuA-RAT — Algebra Question Answering with Rationales (Ling et al., DeepMind, 2017) · train #9379
Stuck? A gentle nudge
No hints for this one.
Your answer
Checked against the answer in AQuA-RAT.