AQuA-RAT train #85222 · Arithmetic · Ratio & rate
P can do a piece of work in 18 days and Q…
P can do a piece of work in 18 days and Q can do in 22 days, with the help of C, they finish the work in 6 days. How long will it take R to finish the work?