AQuA-RAT train #8357 · Algebra · Algebra word problems
A building is to be completed in 48 days
A building is to be completed in 48 days. To meet the deadline 54 men were employed and were made to work for 10 hours a day. After 30 days 5/9th of the work was completed. How many more workers should be employed to meet the deadline if each workers are now made to work 8 hours a day?
AQuA-RAT — Algebra Question Answering with Rationales (Ling et al., DeepMind, 2017) · train #8357
Stuck? A gentle nudge
No hints for this one.
Your answer
Checked against the answer in AQuA-RAT.