AQuA-RAT train #78077 · Arithmetic · Ratio & rate
A and B together can complete a piece of work in 4days
A and B together can complete a piece of work in 4days. If A alone can complete the same work in 12days, in how many days, in how many days can B alone complete that work?
This problem repeats another one in the library (at most with different numbers), so it's left out of browsing.
AQuA-RAT — Algebra Question Answering with Rationales (Ling et al., DeepMind, 2017) · train #78077
Stuck? A gentle nudge
No hints for this one.
Your answer
Checked against the answer in AQuA-RAT.