A can finish a work in 20 days, B in 15 days…

A can finish a work in 20 days, B in 15 days and C in 12 days. B and C start the work but are forced to leave after 2 days. The remaining work was done by A in :

~8 minAnswer checked instantly

AQuA-RAT — Algebra Question Answering with Rationales (Ling et al., DeepMind, 2017) · train #72450

Stuck? A gentle nudge

No hints for this one.

Something off?
Workspace
Your answer

Checked against the answer in AQuA-RAT.