AQuA-RAT train #6960 · Arithmetic · Ratio & rate
12 persons can complete the work in 18 days
12 persons can complete the work in 18 days. after working for 6 days, 4 more persons added to complete the work fast. in how many more days they will complete the work?
AQuA-RAT — Algebra Question Answering with Rationales (Ling et al., DeepMind, 2017) · train #6960
Stuck? A gentle nudge
No hints for this one.
Your answer
Checked against the answer in AQuA-RAT.