Lemma
MediumRatio & rate
AQuA-RAT train #6960 · Arithmetic · Ratio & rate

12 persons can complete the work in 18 days

12 persons can complete the work in 18 days. after working for 6 days, 4 more persons added to complete the work fast. in how many more days they will complete the work?

~8 minAnswer checked instantly

AQuA-RAT — Algebra Question Answering with Rationales (Ling et al., DeepMind, 2017) · train #6960

Stuck? A gentle nudge

No hints for this one.

Something off?
Workspace
Your answer

Checked against the answer in AQuA-RAT.