Lemma
MediumRatio & rate
AQuA-RAT train #68060 · Arithmetic · Ratio & rate

P can do a work in 24 days

P can do a work in 24 days. Q can do the samework in 9 days & R can do the same work in 12 days. Q & R start the work and leave after 3 days. P finishes the remaining work in how many days.

~8 minAnswer checked instantly

AQuA-RAT — Algebra Question Answering with Rationales (Ling et al., DeepMind, 2017) · train #68060

Stuck? A gentle nudge

No hints for this one.

Something off?
Workspace
Your answer

Checked against the answer in AQuA-RAT.