Lemma
MediumAlgebra word problems
AQuA-RAT train #66867 · Algebra · Algebra word problems

6 workers should finish a job in 8 days

6 workers should finish a job in 8 days. After 3 days came 4 workers join them. How many days C do they need to finish the same job?

~8 minAnswer checked instantly

AQuA-RAT — Algebra Question Answering with Rationales (Ling et al., DeepMind, 2017) · train #66867

Stuck? A gentle nudge

No hints for this one.

Something off?
Workspace
Your answer

Checked against the answer in AQuA-RAT.