AQuA-RAT train #63528 · Arithmetic · Ratio & rate

A person P takes 4 hrs time to complete a job and…

A person P takes 4 hrs time to complete a job and Q takes 6 hrs to complete the same job if they work together how much time will they require to complete the job?