AQuA-RAT train #6197 · Arithmetic · Ratio & rate
45 men can complete a work in 14 days
45 men can complete a work in 14 days. Six days after they started working, 30 more men joined them. How many days will they now take to complete the remaining work?
This problem repeats another one in the library (at most with different numbers), so it's left out of browsing.
AQuA-RAT — Algebra Question Answering with Rationales (Ling et al., DeepMind, 2017) · train #6197
Stuck? A gentle nudge
No hints for this one.
Your answer
Checked against the answer in AQuA-RAT.