A certain number of persons can finish a piece of work in…
A certain number of persons can finish a piece of work in 100 days. If there were 10 persons less, it would take 10 more days finish the work. How many persons were there originally?
AQuA-RAT — Algebra Question Answering with Rationales (Ling et al., DeepMind, 2017) · train #6025