AQuA-RAT train #54108 · Arithmetic · Ratio & rate

36 men can complete a piece of work in 18 days.In how…

36 men can complete a piece of work in 18 days.In how days will 27 men can complete the work?

~8 minAnswer checked instantly

AQuA-RAT — Algebra Question Answering with Rationales (Ling et al., DeepMind, 2017) · train #54108