AQuA-RAT train #5144 · Arithmetic · Ratio & rate
If b can complete the work in n days and if a…
If b can complete the work in n days and if a and b can work together then they will complete in y days. what will be time to complete the work a alone?
AQuA-RAT — Algebra Question Answering with Rationales (Ling et al., DeepMind, 2017) · train #5144
Stuck? A gentle nudge
No hints for this one.
Your answer
Checked against the answer in AQuA-RAT.