AQuA-RAT train #51271 · Arithmetic · Ratio & rate
There is a group of persons each of whom can complete a…
There is a group of persons each of whom can complete a piece of work in 16 days, when they are working individually. On the first day one person works, on the second day another person joins him, on the third day one more person joins them and this process continues till the work is completed. How many days are needed to complete the work?
AQuA-RAT — Algebra Question Answering with Rationales (Ling et al., DeepMind, 2017) · train #51271
Stuck? A gentle nudge
No hints for this one.
Your answer
Checked against the answer in AQuA-RAT.