AQuA-RAT train #51271 · Arithmetic · Ratio & rate

There is a group of persons each of whom can complete a…

There is a group of persons each of whom can complete a piece of work in 16 days, when they are working individually. On the first day one person works, on the second day another person joins him, on the third day one more person joins them and this process continues till the work is completed. How many days are needed to complete the work?