AQuA-RAT train #51269 · Arithmetic · Ratio & rate
A,B,C can complete a piece of work in 24,6 and 12 days…
A,B,C can complete a piece of work in 24,6 and 12 days respectively. Working together, they will complete the same work in how many days?
This problem repeats another one in the library (at most with different numbers), so it's left out of browsing.
AQuA-RAT — Algebra Question Answering with Rationales (Ling et al., DeepMind, 2017) · train #51269
Stuck? A gentle nudge
No hints for this one.
Your answer
Checked against the answer in AQuA-RAT.