AQuA-RAT train #476 · Arithmetic · Ratio & rate

Vinoth can complete a painting work in 20 days

Vinoth can complete a painting work in 20 days. Prakash can do the same work in 25 days. They start the work together but Vinoth quit after 3 days of work. How many days are required to complete the remaining painting work by Prakash.