AQuA-RAT train #46524 · Arithmetic · Ratio & rate

Mary completes a piece of work in 160 days, Rose completes the…

Mary completes a piece of work in 160 days, Rose completes the same work in 240 days. If both of them work together, then the number of days required to complete the work is?

~8 minAnswer checked instantly

AQuA-RAT — Algebra Question Answering with Rationales (Ling et al., DeepMind, 2017) · train #46524

Stuck? A gentle nudge

No hints for this one.

Something off?
Workspace
Your answer

Checked against the answer in AQuA-RAT.