Lemma
MediumRatio, proportion & variation
AQuA-RAT train #42891 · Algebra · Ratio, proportion & variation

A team P of 20 engineers can complete work or task in…

A team P of 20 engineers can complete work or task in 32 days. Another team Q of 16 engineers can complete same task in 30 days.Then the ratio of working capacity of 1 member of P to the 1 member of Q is a. 3 : 2

~8 minAnswer checked instantly

AQuA-RAT — Algebra Question Answering with Rationales (Ling et al., DeepMind, 2017) · train #42891

Stuck? A gentle nudge

No hints for this one.

Something off?
Workspace
Your answer

Checked against the answer in AQuA-RAT.