A team P of 20 engineers can complete work or task in…
A team P of 20 engineers can complete work or task in 32 days. Another team Q of 16 engineers can complete same task in 30 days.Then the ratio of working capacity of 1 member of P to the 1 member of Q is a. 3 : 2