Elizabeth can get a certain job done in 15 days, and Tony…

Elizabeth can get a certain job done in 15 days, and Tony can finish only 75% of that job within the same time. Tony worked alone for several days and then Elizabeth joined him, so they finished the rest of the job in 6 days, working together. For how many days have each of them worked and what percentage of the job have each of them completed?