X completes a work in 12 days and Y complete the same…

X completes a work in 12 days and Y complete the same work in 24 days. If both of them work together, then the number of days required to complete the work will be ?

This problem repeats another one in the library (at most with different numbers), so it's left out of browsing.

~8 minAnswer checked instantly

AQuA-RAT — Algebra Question Answering with Rationales (Ling et al., DeepMind, 2017) · train #41055