A project scheduled to be carried out over a single fiscal year…
A project scheduled to be carried out over a single fiscal year has a budget of $12,600, divided into12 equal monthly allocations. At the end of the sixth month of that fiscal year, the total amount actually spent on the project was $6,580. By how much was the project over its budget?