AQuA-RAT train #34090 · Algebra · Algebra word problems
In a plastic company, 14 men working 8 hrs per day complete…
In a plastic company, 14 men working 8 hrs per day complete a piece of work in 12 days. To complete the same work in 6 days, working 14 hours a day, the number of men required is :
AQuA-RAT — Algebra Question Answering with Rationales (Ling et al., DeepMind, 2017) · train #34090
Stuck? A gentle nudge
No hints for this one.
Your answer
Checked against the answer in AQuA-RAT.