AQuA-RAT train #28821 · Arithmetic · Ratio & rate
P and Q can complete a work in 80 days and 48…
P and Q can complete a work in 80 days and 48 days respectively. P alone started the work and Q joined him after 16 days till the completion of the work. How long did the work last?
This problem repeats another one in the library (at most with different numbers), so it's left out of browsing.
AQuA-RAT — Algebra Question Answering with Rationales (Ling et al., DeepMind, 2017) · train #28821
Stuck? A gentle nudge
No hints for this one.
Your answer
Checked against the answer in AQuA-RAT.