AQuA-RAT train #27238 · Arithmetic · Ratio & rate

A can do a piece of work in 12 days and B…

A can do a piece of work in 12 days and B can do a piece of work in 18 days how many days will the work be completed if both of them work together?

~8 minAnswer checked instantly

AQuA-RAT — Algebra Question Answering with Rationales (Ling et al., DeepMind, 2017) · train #27238