AQuA-RAT train #23823 · Algebra · Algebra word problems
In a nuts and bolts factory, one machine produces only nuts at…
In a nuts and bolts factory, one machine produces only nuts at the rate of 100 nuts per minute and needs to be cleaned for 5 minutes after production of every 1,000 nuts. Another machine produces only bolts at the rate of 75 bolts per minute and needs to be cleaned for 10 minutes after production of every 1,500 bolts. If both the machines start production at the same time, what is the minimum duration required for producing 9,000 pairs of nuts and bolts?
AQuA-RAT — Algebra Question Answering with Rationales (Ling et al., DeepMind, 2017) · train #23823