AQuA-RAT train #17672 · Arithmetic · Ratio & rate

A can do a piece of work in 40 days; B can…

A can do a piece of work in 40 days; B can do the same in 30 days. A started alone but left the work after 10 days, then B worked at it for 10 days. C finished the remaining work in 10 days. C alone can do the whole work in?