AQuA-RAT train #17444 · Arithmetic · Ratio & rate

A alone can do a piece of work in 6 days and…

A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?

~8 minAnswer checked instantly

AQuA-RAT — Algebra Question Answering with Rationales (Ling et al., DeepMind, 2017) · train #17444