AQuA-RAT train #17234 · Algebra · Algebra word problems
12 men work 8 hours per day to complete the work in…
12 men work 8 hours per day to complete the work in 10 days. To complete the same work in 10 days, working 12 hours a day, the number of men required?
AQuA-RAT — Algebra Question Answering with Rationales (Ling et al., DeepMind, 2017) · train #17234