The city of Boston decided to reconstruct its major tunnels
The city of Boston decided to reconstruct its major tunnels. It estimated the job would require 612 mini projects spread evenly over an 18 month plan of completion. Only 108 mini projects had been successfully completed after 8 months. At this time, the construction was behind schedule by how many projects?