Abel can complete a work in 8 days, Ben in 12 days…
Abel can complete a work in 8 days, Ben in 12 days and Carla in 15 days. All of them began the work together, but Abel had to leave after 2 days and Ben 3 days before the completion of the work. How long did the work last?