A person X working alone can complete a work in 5 days
A person X working alone can complete a work in 5 days. A person Y completes the same amount of work in 20 days, and a person Z when working alone can complete the same amount of work in 30 days. All three people work together for 2 days but then X and Y leave. How many more days does Z need to complete the work after X and Y leave?
AQuA-RAT — Algebra Question Answering with Rationales (Ling et al., DeepMind, 2017) · train #15345
Stuck? A gentle nudge
No hints for this one.
Your answer
Checked against the answer in AQuA-RAT.