AQuA-RAT train #15243 · Algebra · Algebra word problems

A furniture manufacturer has two machines, but only one can be used…

A furniture manufacturer has two machines, but only one can be used at a time. Machine E is utilized during the first shift and Machine B during the second shift, while both work half of the third shift. If Machine E can do the job in 12 days working two shifts and Machine B can do the job in 15 days working two shifts, how many days will it take to do the job with the current work schedule?