AQuA-RAT train #15060 · Arithmetic · Ratio & rate

P, Q and R can do a work in 20, 30 and…

P, Q and R can do a work in 20, 30 and 60 days respectively. How many days does it need to complete the work if P does the work and he is assisted by Q and R on every third day?

~8 minAnswer checked instantly

AQuA-RAT — Algebra Question Answering with Rationales (Ling et al., DeepMind, 2017) · train #15060