AQuA-RAT train #11498 · Arithmetic · Ratio & rate
It takes 2 team of farm workers 12 days to completely prepare…
It takes 2 team of farm workers 12 days to completely prepare a piece of land for planting. if both team of workers were to work separately, one of them can complete the work 10 days earlier than the other, how many days will it take each of them to separately complete the work?
AQuA-RAT — Algebra Question Answering with Rationales (Ling et al., DeepMind, 2017) · train #11498
Stuck? A gentle nudge
No hints for this one.
Your answer
Checked against the answer in AQuA-RAT.