AQuA-RAT train #10601 · Arithmetic · Ratio & rate
P can do a work in 24 days
P can do a work in 24 days. Q can do the same work in 9 days and R can do the same in 12 days. Q and R start the work and leave after 3 days. P finishes the remaining work in --- days.
AQuA-RAT — Algebra Question Answering with Rationales (Ling et al., DeepMind, 2017) · train #10601
Stuck? A gentle nudge
No hints for this one.
Your answer
Checked against the answer in AQuA-RAT.